The Most Undiscussed Aspect of Piling Jobs

·

·

If you ask someone what happens on a piling job, they will explain the drilling: the rig, an auger spinning down, and concrete being pumped down, and it all sounds very impressive. However, the actual make or break factor for job success is the lifting and handling.

For some reason, people do not get excited about logistics, at least not until they have reason to care. Things like concrete wagons not being efficiently placed, reinforcement cages not being able to fit through site access, and having to figure out what to do with 3 tonnes of spoil sitting in the exact same spot as the next pile.

Steel reinforcement cages. The unsung heroes of the piling job.

Steel reinforcement cages are no walk in the park. Given the actual size of the pile, it will range from a few hundred kilos to over a ton, not something you can toss in the back of the guy. These cages are not only heavy, but they are long, a bit awkward, and can easily be damaged if not handled properly.

It’s crucial to have a plan in place for deliveries. We receive deliveries from flatbeds and articulated vehicles. It is important to know in advance if your site has narrow access lanes, or if your site has tight turns, so drivers do not arrive and find themselves unable to deliver. We once received a delivery of cages, and the truck had to deliver them to a nearby location. After we received the cages, we had to hire a crane to lift the cages over some buildings.

Storage is also an important factor to consider for your delivery. Cages that are stored in soft ground will be more difficult to lift, and they become more damaged. Cages need to be stored on flat and hard surfaces to avoid them being constantly knocked over to create more free space. Cages that become bent or twisted are useless, and cannot simply be pounded back into shape.

To finish the job and get them into position, a telehandler or crane will be necessary. It is important that there is enough room to work on finishing the job safely without leaving a piling rig idle to complete the job. Rigs charge by the day, so be sure to avoid in idle time.

In the Piling process we use concrete quickly. One of the decent CFA piles is several cubic meters of concrete, and we are installing several piles daily. We need the deliveries to arrive at the site to keep the operation on schedule. It is important to have the concrete delivered to the site on time. We are on a tight schedule and cannot have the concrete delivered to the site too early or too late.

Ready-mix wagons are large and extremely heavy vehicles. They require enough access to find a place to turnaround and rest on solid ground. This is fine on a greenfield site where there is enough mobility. However, this is not the case on tight urban sites or anywhere where there is restricted acces.

If wagons can’t get close enough, there is the need for concrete pumps. This requires more equipment, which increases cost and coordination complexity. The pumps require set up, need to be cleaned after every load, and need to be positioned in a way that minimizes the hose dragging.

There is a one way to get out of a tight situation, and that is to watch the timing. If there a delays with the cage, or there are problems with the pile, you may be left with a wagon full of concrete that is worthless. If the concrete is allowed to set, it must be disposed of, and that is a cost that must be dealt with by someone.

Getting spoil off site

Spoil is created when every pile is created – excavated soil and groundwater. Over a job, that is an enormous amount of material that has to go somewhere.

On open sites, this can be loaded straight into muck-away wagons. Spoil is left for a few hours, a grab wagon comes in and the spoil is removed.

On restricted sites, it is a little more complicated. If wagons can’t get in, spoil needs bagging or moving in smaller vehicles. Working inside existing buildings might mean carrying it out by hand or pumping it as a slurry. Either way, it takes time and needs to be added into the programme.

Most of the time, clean soil goes to the landfill, or it gets reused right at the site. Contaminated soil needs to be tested, and its disposal needs to be arranged properly, which takes additional time and costs more.

What Goes Wrong

One job we did a couple of years back in the residential area looked straightforward. The concrete trucks had to back in, but it blocked the road, and the neighbors got upset and called the council. We had to bring in a pump at additional costs and more setup time every day.

The delivery of storage reinforcement cages was forgotten, and we had to prop them up on a wall on uneven ground. When we needed them, two were used, and the replacements had to be ordered while the job was delayed three days while we waited on their delivery.

Spoil removal was not appropriately handled. The initial plan was to clear it weekly, but after two days, and the blocked concrete pump, there was no space for the spoils of the ongoing piles. Daily collections had to be arranged at a higher cost, which had not been included in the plan.

None of the problems were complicated, but combined, they turned a two-week job into almost four with the additional costs for equipment, wasted materials, and extra site visits. All of this was due to a lack of lifting and handling planning.

Getting it right

Before work starts, stroll through the site with the contractor, step by step. How are materials getting delivered? Where will they be stored? What lifting equipment is required? How is spoil removed? Where is the rig actually working from?

If they are assuming a piece of lifting equipment is already on site, and you assume they are bringing it, this will cause issues. Confirm what lifting equipment they are bringing versus what they are expecting on site.

There must be space for everything. Make sure there is space for the rig and access for concrete wagons, storage for the spoil without blocking paths, and space for the cages.

Remember to factor time for moving/storing cages, filling, or emptying the spoil, and consolidation for the concrete around the average time to complete a pile. With 20 minutes on either side for moving spoil, the average number of piles that will be installed every day changes.

The drilling is the impressive part, and that is where the skill is. But the boring stuff around the edges – the logistics, the lifting, the handling – that is what turns your piling job into an expensive lesson on what to do, or not do, for the next time.